The construction of the new district project is progressing smoothly
Author:
To ensure the timely production of the new district project, the construction unit utilized the current sunny weather, worked overtime, and the construction site was in full swing, with the project construction solidly advancing.
Recently, the main steel structures of buildings 1 #, 2 #, and 3 # have all been installed and are currently being coated with fire-resistant paint. They have entered the stage of enclosure installation.
The office building is capped.
The comprehensive building will be constructed to the second floor.

The construction of the fire pump room, main gate, outdoor plant area, and other ancillary projects is about to commence.
The next step will be to fully promote the construction of the new area. Guided by the new development concept, with high standards and strict requirements, focusing on quality to promote progress, we strive to build the new area into a first-class factory in the national conveyor industry.
永生机械
Related News
Contact Us
Procurement hotline: 0556-6217265
After-sales service: 0556-6217261
Address: No. 25 Heping East Road, Tongcheng Economic Development Zone, Anhui Province
Follow us